Published: 17 November 2026
Al Maktoum International Airport will be tested for at least a year before its first passenger walks through the doors, Dubai Airports chief executive Paul Griffiths said at a media briefing on Tuesday. The first phase of the $35 billion project in Dubai South is due to open in 2032, and more than 100,000 workers are already on site, according to The National and Gulf News.
Al Maktoum International Airport testing plan
The National reports that the trial period will cover baggage handling, check-in, Wi-Fi and other airport technology. Dubai International (DXB) stays open throughout, which lets the operator try the Al Maktoum International Airport systems on a live airport before anyone migrates.
“There will be at least a year of testing before we even allow the first customer to cross the threshold,” Griffiths said. He described the move itself as unprecedented, noting that Hong Kong shifted about 20 million passengers when it changed airports in the 1990s, while Dubai’s operation will be five or six times larger. The two airports will run side by side for a time before operations are condensed into one.
Construction progress and contracts
“There are more than 100,000 workers on site. Piling is commencing. Groundworks are well under way,” Griffiths said, adding that major contracts are being discussed. Gulf News adds that in June the project team reported more than 17,000 concrete piles installed and over 45 million cubic metres of earth excavated, with the workforce expected to peak near 120,000.
The National notes that Dubai Airports awarded Dh13 billion of terminal contracts this year, with another Dh55 billion to follow by the end of 2026. At Al Maktoum International Airport, contracts for the baggage system and automated people movers are still under discussion. The first phase will handle 150 million passengers a year, rising to 260 million passengers and 12 million tonnes of cargo at full build-out.
A new city for airport workers
Griffiths called Al Maktoum International Airport far bigger than an airport project. “We are taking the entire top left corner of Dubai and transplanting it in the bottom right-hand corner, 70km away,” he said. Staff based in Dubai and the Northern Emirates cannot make that commute daily, so new communities will be needed for airport-sector workers.
For buyers, that is the part to watch. Our report on the Dubai Metro extension to Al Maktoum covers the transport side, and our guide to freehold areas in Dubai for foreigners shows where overseas buyers can own today. Because completion is years away, many will compare off-plan and ready property before choosing a Dubai South location.
Frequently Asked Questions
When will Al Maktoum International Airport open to passengers?
The first phase is due to open in 2032, according to The National and Gulf News. Dubai Airports chief executive Paul Griffiths said the airport will be tested for at least a year beforehand, so the first customer will not be admitted until that trial period has finished.
How many workers are building the new Dubai airport?
Griffiths said more than 100,000 workers are on site at the $35 billion development, with piling and groundworks under way. Gulf News adds that the project team had earlier expected the workforce to reach about 120,000 at the peak of construction, based on figures given in June.
What capacity will the new airport have?
The first phase will handle 150 million passengers a year. When the airport is complete, capacity is planned to reach 260 million passengers and 12 million tonnes of cargo annually, according to The National, with Gulf News reporting that the master plan includes five runways.
Why are new communities needed near the airport?
Griffiths said airport staff living in Dubai and the Northern Emirates cannot commute about 70 kilometres to the new site every day. The National reports that new communities will have to be built closer to the airport to house workers in the aviation sector.
Sources
- The National: Al Maktoum airport to undergo a year of testing before first passengers arrive (17 November 2026)
- Gulf News: Dubai’s $35 billion Al Maktoum airport project: Over 100,000 workers on site, says CEO (17 November 2026)
Ready to start investing in Dubai?
For free consultation and access to the latest property opportunities in Dubai and the UAE,
get in touch with Master Real Estate.
We guide you in choosing the right project, reviewing payment plans, obtaining residency,
and building a secure and profitable investment strategy.
With access to updated below-market property listings and expert market insights,
you can confidently make decisions and start your Dubai property journey the smart way.
Explore Dubai Off-Plan Projects